I-95 Rehabilitation


Location I-95 North of the Fort McHenry Tunnel to I-895 in Baltimore, MD
Duration November 2004 - November 2006
Description Scarifying and Latex Modified Concrete overlay of 22 bridge decks, related bridge joint and parapet work, steel repairs to bridges, sign structures and related miscellaneous work.

Brooming on the bond coat, used to assure bonding between the original deck surface and the latex concrete overlay.

While striking off the concrete to finish grade, crewmembers control the amount of concrete in front of the finishing machine rollers with concrete hoes.

After the concrete is finished to grade, the concrete overlay is covered with wet burlap and polyethylene during the wet cure period.