Wagman

Chesapeake Bay Bridge


Location SR 50 crossing the Chesapeake Bay, near Annapolis, MD 220x220
Duration 2004-2005
Description Wagman was called upon to replace the concrete overlay on a portion of the Chesapeake Bay Bridge. Responding quickly, Wagman replaced 2.5 lane miles by early November 2004 to allow traffic restrictions to be removed in advance of cold weather. In April 2005, Wagman returned to the project to replace an additional 1.5 lane miles. A total of 2440 cubic yards of Latex Modified Concrete was used to successfully complete the new concrete overlays.